07 Dec 2020
GEA heat pump system installed at Bunhill 2 Energy Centre, Islington, central London. (Photo: Islington Council)
Paddy McGuinness, Managing Director of Colloide Engineering Systems, adds: “Colloide has been involved in several renewable energy projects. We partnered with GEA. on this project given their knowledge of ammonia refrigeration and heat pump technology. Based on GEA’s experience, 95 percent of the industrial refrigeration plants installed over the last 10 years have been ammonia based. Increased pressure to reduce energy bills for end users is driving a lot of interest in ammonia heat pumps.”
Exterior of Bunhill 2 Energy Centre, Islington, central London. (Photo: Islington Council)
The Bunhill 2 Energy Centre now connects an additional 550 homes and a primary school to the existing Bunhill Heat and Power district heating network, launched by the Islington Council in 2012. The heating costs for residents connected to the network will be cut by 10 percent when compared to other existing communal heating systems, which themselves cost around half as much as standalone systems for heating individual homes. The new system is a win-win for the environment and for the residents of Islington and aligns with the council’s aim to end fuel poverty.
The heating system is particularly environmentally friendly as it reuses heat that would otherwise be wasted. Supplying the connected households and public facilities with the upgraded waste heat will help to reduce CO2 emissions in the Islington Borough by around 500 tons per year.
“Thanks to the cooperation of all involved, this is a ground-breaking district heating scheme. The main technology used is the ammonia heat pump and as a result, this project provides cheaper, greener energy for the local community,” states Shaun Hannon, Contracts Manager at Colloide.
GEA’s Kenneth Hoffmann (left) and Iain Eckett (right) at Bunhill 2 Energy Centre, Islington, central London
Iain Eckett, Technical Sales Manager, Refrigeration Technologies, GEA UK, concludes: "This was a very ambitious task. But we have shown that GEA has the knowledge, the technology and the ability to successfully implement innovative projects to generate cleaner and cheaper heating. We offer the most efficient solution at an attractive price."
The principle of heat recovery using heat pumps can be applied in London and in underground networks all around the world. London alone has more than 150 ventilation shafts where waste heat could potentially be recovered. GEA heat pump technology, coupled with the experience gained from groundbreaking projects like the Bunhill 2 Energy Centre in Islington, has made GEA a trusted and preferred partner for waste heat projects globally.
Start: 2017
Completion: 2019
Opening: 2020
Gross internal floor area: 617m²
Contract: JCT Design and Build Contract
Architects: Cullinan Studio (design),McGurk Chartered Architects (delivery)
Client and project manager: Islington Borough Council
Key delivery partner: Transport for London
Structural engineer: Ramboll (design), McMahon Associates (delivery)
M&E Consultant: Ramboll
QS: Gleeds
Landscape consultant: J&L Gibbons
CDM Coordinator: AECOM
Approved building inspector: Islington Building Control
Design and build contractor: Colloide Engineering
Artist: Toby Paterson
Heat pump system: GEA (design, manufacture, and installation)
Testing and Commissioning: Topic Plan
Project consultant: Inner Circle Consulting
Rights of light: Right of Light Consulting
CAD software: MicroStation, Revit
Media Relations
GEA Group Aktiengesellschaft
Peter-Müller-Str. 12
40468
Düsseldorf
Germany
+49 211 9136-0
GEA è fra i principali fornitori dell'industria di processo alimentare e di una vasta gamma di altri settori. Nel 2019 ha realizzato un fatturato consolidato di circa 4,9 miliardi di euro.